Newark Liberty Airport
- Aug 8, 2019
- 1 min read
Earlier this summer at the Terminal A Redevelopment Program at Newark Liberty Airport, Stonebridge Steel Erection erected main terminal steel with a Manitowoc 2250 crawler crane using working drawings prepared by Siefert Associates, LLC. The crawler crane is to operate on a 575ft [±] x 40ft crane pad, and is to erect steel out to 160ft radius. Photos below taken during crane foundation inspection, performed by Siefert Associates, LLC.